Ahead of Schedule: Repair of 6,000 Meters Sewage Pipeline Completed in Lujhou Nangangzi

Reported about 1 year ago

In the Lujhou Nangangzi redevelopment area in New Taipei City, the construction progress for sewage pipeline construction and repair work has reached 75.91%, ahead by 7%, with 6,000 meters of sewage pipeline already repaired. With the project expected to be fully completed by the end of the year, it will significantly improve the environmental hygiene quality of the area. Using non-excavation method, the project has extended the life of sewage pipelines by 30 years by improving the structure and hydraulic characteristics. Residents are expressing their satisfaction with the progress, as the project will eliminate the need for septic tanks and enhance living conditions.

Source: YAHOO